Decommissioning

Pre-Submission
Consistency Review

A fixed-fee, independent check that the documents in a decommissioning submission reconcile with each other and with published requirements, carried out before a gate rather than after a query.

What it is

We read the documents that make up your submission as one set. Sixteen checks look for places where the documents disagree - quantities, boundaries, options, costs, dates and figures - and for places where a published requirement is not visibly met.

The output is a findings table you can hand to the document owners, and a one-page readiness summary for the gate.

Who it is for

Operators’ decommissioning teams: programme leads, regulatory and environmental leads, and those who sign off a submission and want an independent set of eyes on its consistency first.

Examples of the checks

  • Components, quantities and boundaries agree across the DP, CA, EA and safety case.
  • The preferred option in the programme matches the comparative assessment outcome; any departure from the lowest-scoring option is explained.
  • Cost basis, contingency and withheld figures are stated.
  • Rock, vessel-day and emissions figures agree between the CA and the EA.
  • The dismantling safety case covers every Schedule 8 particular.
  • The verification scheme is revised before the safety-critical element record changes.

The gate model (version 0.1)

Six gates, each with a question the documents should be able to answer. The model is proposed and is being validated with practitioners.

GateNameQuestion at the gateMain documents
G0Cessation planningAre the decommissioning scope, cost basis and timing defined?Cessation case, scope inventory, cost estimate
G1Option assessmentAre the options complete, screened and scored defensibly?Comparative assessment, CA workshop record
G2Programme submissionDo the programme and environmental assessment match the CA outcome and each other?DP, EA, consultation record
G3Pre-dismantling readinessIs the revised safety case accepted and the verification scheme revised?Safety case, risk assessment, verification scheme, well notification
G4Phase transitionBefore each substantive phase, are risks, the safety-critical element record and verification updated?Phase risk assessment, element record, verifier comment
G5Close-outAre seabed clearance, monitoring commitments and lessons recorded?Close-out report, clearance statement, survey plan

Gates G0, G1, G2 and G5 are being confirmed against current OPRED guidance. Gates G3 and G4 rest on the Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015 (SI 2015/398) and HSE Information Sheets 2/2008 and 3/2006.

Phase-gate methodology: six gates and sixteen consistency checks

What you receive

01
Findings table
Each inconsistency or unmet requirement, where it appears in each document, and which check it falls under - ready to pass to the document owner.
02
Readiness summary
One page for the gate: what reconciles, what does not, and what needs an owner’s decision before submission.
03
Context from the public record
Where relevant, how comparable documents among the 363 we have read handle the same point. Descriptive, not a benchmark.

No-cost pilot

Sixteen checks over two weeks on one approved public document set - for example, one of your own approved programmes - with a findings table and a one-page readiness summary. It shows what the review looks like on a real submission before you commit to anything. Scope and timing are agreed in a short call.

Request a Pilot

Limits

The checks draw on the Knowledge base: a Decommissioning BOK, a Regulatory BOK and a regulatory checklist. Further detail, including the evidence base and its limits, is in the Practitioner Guide and the Theoretical Guide (PDFs).