Two bodies of knowledge built from public documents, and a working checklist built from them. They inform the Pre-Submission Consistency Review. They are not a separate offer, and they are kept plain about what they can and cannot show.

01
Decommissioning BOK
A structured reading of 363 public decommissioning documents: 203 programmes, 70 environmental assessments, 55 comparative assessments and 35 close-out reports. It shows how real submissions are written and where they drift apart.

Factsheet (PDF) ↓
02
Regulatory BOK
What regulators and statute say about programmes, comparative assessments and environmental appraisals, with the environmental and offshore safety rules around them. 78 sources registered, 70 distinct and usable. Version 2.1, 30 October 2026.

Factsheet (PDF) ↓
03
Regulatory Checklist
A 110-line working checklist in ten sections, each line citing its source in the Regulatory BOK, with applies codes, status, owner and a watch list of rules that may change. Plus a titles-only coverage register of the public document folders.

Factsheet (PDF) ↓
363
Documents read

Counts are of documents read, not of the UKCS. 323 approved, 37 draft, 3 unclassified.

78
Regulatory sources registered

73 extracted and 70 distinct and usable. Four members-only sources are listed but not downloaded.

110
Checklist lines

Ten sections from early planning to close-out and liability. Each cites a source and page.

How the Regulatory BOK stays honest

Four rules, applied to every statement.

TagMeaning
FFinal guidance, statute or published regulator document
DDraft or consultation document, not settled
UUnofficial consolidation or secondary text; check the official version
WWeb page as captured on the date of the run
EExemplar report from a single case; indicative only

Sample: two conflicts, shown not resolved

TopicSource ASource B
Post-disposal report deadlineDP-01 p.70: within a year of completing the disposalOSPAR-01 p.3: within six months. Confirm with OPRED.
Jacket cut depthDP-01 pp.35, 38: aim 3 m below seabed (final)CA-03 web: seabed level or shallow cut proposed (draft, not settled)

Sample: four checklist lines

RefCheckSource
1.4Early discussion held with OPRED and an outline timetable given.DP-01 pp.23, 133
2.7OSPAR consultation planned to start at least 32 weeks before the planned decision (derogation cases).OSPAR-01 p.4
8.2NSTA suspension or abandonment application submitted 28 days before operations.NSTA-09 p.1
10.1Close-out report submitted within one year of completing offshore work, with debris clearance and post-decommissioning survey results.DP-01 pp.24, 68

How the method fits together

The review is organised as a phase-gate model with six gates and sixteen checks. Version 0.1 is proposed and is being validated with practitioners.

Phase-gate methodology: six gates and sixteen consistency checks
A
Gate discipline
Gates, stage boundaries, exceptions and lessons learned follow the stage-gate practice set out in PMBOK and PRINCE2, used as informative guidance.
B
Regulatory spine
Gates three and four rest on the Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015 and HSE guidance. Other gates are being confirmed against OPRED guidance.
C
Improvement loop
Lean Six Sigma supplies the loop: findings become owned actions, measured at the next gate. The method author has written and taught a Level 6 Lean Six Sigma module set.
D
Checklist and evidence
From aviation: written checklists, challenge before commitment and a standard of evidence. The author has flown since 1989 and holds a flight instructor rating (CFII).

These frameworks are used as informative guidance. Meginráð is not an accredited body for any of them, and the review is not certified against them.

What is public, and what is not

Contents, counts, status tags, sample extracts and the factsheets above are public. The full BOKs, the checklist template and the extraction database are shared with pilot clients or on request. Exemplar documents belong to their operators and are described here, not republished. Members-only industry guidance is listed as a gap, not reproduced.

See the full set on a real document set

The no-cost pilot uses the BOKs and checklist on one approved public document set, and returns a findings table and a one-page readiness summary. To see the full BOKs first, ask.

Request a Pilot or the Full BOKs

Informative guidance only. Built from public documents and guidance as read on 30 October 2026. Not legal advice, a regulatory approval, a safety verification or an engineering design review. Confirm live requirements with OPRED, NSTA and HSE.